Ghana’s power problems could last two more years – Eenergy Analyst warns

Energy analyst Kwadwo Nsafoah Poku has warned that Ghana’s power challenges could last at least two more years, and he blames weak investment in electricity transmission over the past two years.
Speaking on JoyNews’ Newsfile on Saturday, November 28, Mr Poku said the shortfall in spending on the transmission network helped cause the current situation and will keep affecting how reliable electricity supply is.
“The problem is the lack of investment in the last two years in the transmission,” he said.
He said the country is unlikely to see relief soon, even if government releases money for new transmission projects, because awarding contracts and completing the infrastructure takes time.
“Immediately, we are going to have this problem for the next two years. Two years,” he said.
His assessment comes as government sets aside funds for transmission in the 2027 Budget. Mr Poku referred to an allocation of 500 million announced by the Energy Minister for transmission under the new economy. He questioned how quickly it would turn into finished projects and better supply, and said it will not solve the immediate problems because building transmission infrastructure is a long process.
“Today, if you’re going to give money to GRIDCo in 2027, how long do you think something will take?” he asked.
He also questioned government’s decision to cancel an agreement with the German development bank KfW, and the delay in acting on a 50 million World Bank funding arrangement meant for the transmission sector. He said government inherited two agreements when it took office in January 2025, and that cancelling the KfW deal has raised doubts about whether funding will be available for the projects needed. The country, he argued, cannot afford more delays in closing gaps in the network.
To show how long such projects take, Mr Poku pointed to the K1 and K2 transmission lines, which he said are still being worked on. They include the Anwomaso-Ahodwo line, which he said is not yet fully complete more than two years after the contract was awarded.
“We awarded the K1 and K2 they are talking about in July 2024. You are talking about a shutdown three days ago to now operationalise that line,” he said.
He said the K1 and K2 timeline shows why government should not expect transmission to improve right after it announces new funding. Fixing the problem, he said, needs sustained investment and timely delivery of transmission projects, not budget allocations alone.